Budget: 

The consumed budget for speed bump power generator is divided into three categories; first category is for buying parts that do not need machine and manufacture such as rack, pinion, and shaft. Second category is buying raw materials in order to machine and manufacture parts for the device such as, top and bottom plates, rod supports, and cap for the top plate. Third category is rebuying parts or raw materials instead of parts that have machined wrongly. 80% of the budget was used for buying and manufacturing the parts of the device, while 20% was used to solve the manufacturing issues. The team has spent $173 on buying all the needed parts. Moreover, all the needed parts were ordered, made, and done by group members based on the manufacturing plan and ahead of time which allows the team to be ready for testing the device. All the parts that Will be needed to build the device are ready and have no issue that may affect the building process